vertical cement mill operation process parameters
Cement vertiacal mill is one kind of roller mill. As requested, it may equip with 3-4 rollers. Each roller is composed of fixed roller, support of installation rocker arm and hydraulic system. Motive force unit is in the whole or a standard part. It can be arranged in two compontents, three compontents or four compontents around mill grinding table.
Work Principle:
Raw material feed into discharege pipe through rotary discharger. Discharge pipe enter into the mill through the side or the center of separator. Material will fall into the center of mill disc with the help of gravity and air flow. Mill disc connect with the reducer constantly. Constant speed rotation of mill disc will distribute materiao evenly in the lining plate of mill disc. There inclined mill roller will be bite material and pulverize. Grind material with the function of pressure and friction. Centrifugal force will make pulverized material at the edge of mill disc from the middle of mill disc. Material off mill disc will enter into hot gas in the mill through air ring. Via the middle of the mill shell and enter into the separator. During the process, material will exchange hot gas. The moisture will be evaporated. The rest moisture can reach 1%. Unpulverized material as request will be selected by the separator and send back grinding table.
Main Technical Parameter of cement vertical mill: